Parkington Plaza

Parkington Plaza

Edmonton, Alberta

PROJECT SUMMARY
End Use: Office
Size: 20,820 sq. ft.

Project Delivery Method:
Construction Management
Consultant: Hodgson Schilf
Completed: December 2015
Project Scope: Faҫade Renovation
Notes: Stucco and window replacement, asbestos abatement and mold removal.

ATCO Gas Operations Centre

ATCO Gas Operations Centre

Red Deer, Alberta

PROJECT SUMMARY
Built on 6.3 acres of land in Red Deer’s Edgar Industrial Park, this 35,000 sq. ft. facility was designed in a T shape with the bottom leg housing a wash bay, stores, shop/maintenance space, emergency vehicle storage space, pipe threading and fustion rooms as well as related office and staff areas. The top of the T houses the administration of the three main field groups including private offices and bull pen areas, meeting and training rooms, and conference room. This was a Design-Build project and Atco had their Key Department Heads participate directly with Scott design staff…as a team, during the entire design phase resulting in an exceptionally functional and attractive facility.



Project Delivery Method:
Design | Build
Design Build Team: ATCO Gas Operations Centre, Scott Builders, Bearden Engineering Consultants Ltd.

Stantec

Stantec

Red Deer, Alberta

PROJECT SUMMARY:
End Use: Office
Size: 6,600 sq. ft.
Scope of Work: Completed tenant improvements for the 7th and 11th floors

 

Project Delivery Method:
Project Management
Consultant: Stantec Architecture
Completed: July 2014

Finning

Finning

Red Deer, Alberta

PROJECT SUMMARY:
Size: 231,300 sq. ft.
110,000 sq. ft. office (3 storey) & shop
115,000 sq. ft. second shop
6,300 sq. ft. wash bay facility & mechanical shop
Site: 25 acres

Project Delivery Method:
Design | Build
Consultant: Group 2 Architecture
Completed: Construction was completed in phases between 2000 – 2008

Chatters Canada Ltd.

Chatters Canada Ltd.

Red Deer, Alberta

PROJECT SUMMARY:
End Use:  Office/Warehouse
Professional Beauty Supplies
Size: 23,000 sq. ft.
11,000 sq. ft. Office

Project Delivery Method:
Design | Build
Completed: Spring 2008
2011 Addition:
13,000 sq. ft. Warehouse Space

Trican Well Service Ltd.

Trican Well Service Ltd.

Red Deer, Alberta

PROJECT SUMMARY:
End Use: 
Office/Shop
Size: 21,500 sq. ft.
4,000 sq. ft.  Warehouse

Project Delivery Method:
Project Management
Completed: March 2005
Notes:
Scott Builders has completed 15 projects across Western Canada for Trican. Locations include: Grand Prairie, Nisku, Whitecourt, Redcliff, Medicine Hat, and in British Columbia, Fort Nelson and Fort St. John.
Most recently completed a project in Brandon MB in 2013

Target Safety

Target Safety

Lloydminster, Alberta

PROJECT SUMMARY:
End Use: Shop/Office
Size: 12,250 sq. ft.
Site: 1.5 acres

Project Delivery Method:
Design | Build
Consultant: Berry Architecture
Completed: February 2014

Entrec

Entrec

Acheson, Alberta

PROJECT SUMMARY:
End Use: Shop/Office
Size: Phase 1: 76,000 sq. ft.
Site: 36.92 acres

Project Delivery Method:
Construction Management
ConsultantDavid Wong Architect Ltd.
Completed: July 17, 2014

Canexus

Canexus

Red Deer, Alberta

PROJECT SUMMARY:
End Use: Office/Warehouse
Size: 35,000 sq. ft.
Size: 6 acres

Project Delivery Method:
Project Management
Consultant: Bearden Engineering Consultants Ltd.
Completed: April 2005

Arnett & Burgess Pipeliners Ltd.

Arnett & Burgess Pipeliners Ltd.

Athabasca, Alberta

PROJECT SUMMARY:
End Use: Shop/Office
Size: 19,288 sq. ft
Site: 139 acres

Project Delivery Method:
Design | Build
Consultant: Cognidyn Engineering & Associates
Completion: May 2014
Building Partner since 2010, four locations constructed