Executive Summary
Scott Builders delivered a $15M renovation and expansion of the Gary Moe Auto Sportsplex in Lacombe, Alberta, transforming a dated sports facility into a state-of-the-art community hub. This four-phased project was completed on schedule and within budget while the facility remained fully operational. The team navigated significant structural challenges with innovative engineering strategies and transparent communication, while maintaining a flawless safety record. The result is a vibrant, modernized facility that reflects Scott Builders’ commitment to excellence, safety, and consistency, every step of the way.
Introduction
Renovating and expanding actively used community spaces is no small feat, but it’s a challenge Scott Builders is equipped to handle. The Gary Moe Auto Sportsplex project is a testament to our ability to exceed expectations with seamless alignment, even when faced with hurdles like structural complexities and budget constraints. This case illustrates not only how we delivered on time and on budget but also how we created a welcoming environment for community members, schools, and sports enthusiasts—all while the facility continued its day-to-day operations.
The Challenge
This project was exceptionally challenging, requiring careful scheduling and coordination. At one stage, structural shoring was used to support the main building while new foundations were installed, keeping the indoor pool and two ice arenas fully operational throughout.
The exterior work added complexity, as nearby schools required precise planning to avoid disrupting recess, lunch breaks, and bus traffic. Additionally, we used shoring to support ice arena bleachers during foundation work and dressing room renovations underneath, allowing uninterrupted public access to the bleachers as construction continued.
Furthermore, effective stakeholder coordination played a crucial role in the project's success. Strong collaboration among city officials, educational institutions, and facility operators ensured seamless execution and impactful outcomes.
Solutions
To overcome these challenges, Scott Builders implemented strategic planning, technical expertise, and innovative problem-solving techniques.
-
Phased Construction Approach
The project followed a meticulously organized four-phased construction timeline, allowing different portions of the facility to remain open for use. Clear scheduling and adaptive work plans minimized disruptions to end users. -
Innovative Engineering
Unforeseen foundation issues were resolved through advanced engineering solutions. The team worked in tandem with structural experts to stabilize the site effectively, ensuring all construction remained on track. -
Stakeholder Engagement
Scott Builders held regular meetings with stakeholders—including local schools and facility operators—to ensure all community members were informed and their needs addressed. This collaborative approach fostered trust and transparency throughout the project lifecycle. -
Unwavering Focus on Safety
Across the two-year construction period, Scott Builders maintained a perfect safety record with zero incidents. Rigorous safety protocols and proactive training sessions ensured a secure work environment for workers and facility users alike.
Key Achievements
- Complexity Managed: Successfully delivered a 119,963 sq. ft. renovation and expansion while maintaining full operational capacity.
- Foundation Challenges Resolved: Overcame significant structural and foundation issues using innovative engineering solutions.
- Budget and Schedule Adherence: Completed all four phases on schedule and within the $15M budget, even with unexpected delays and complications.
- Flawless Safety Record: Achieved zero incidents over the entire two-year construction window.
- Stakeholder Collaboration: Ensured seamless coordination among community stakeholders for minimal disruption.
Results
The Gary Moe Auto Sportsplex now stands as a dynamic, modernized facility equipped to handle the growing needs of the Lacombe community. From upgraded sports amenities to enhanced aesthetics, the renovation significantly elevates user experience while fostering community pride.
Key Data Points:
- Size: 119,963 sq. ft.
- Budget: $15M
- Safety Record: Zero incidents
- Completion Time: Two years
Quotes
“I am incredibly proud of all the precise scheduling with all parties and without any incidents , accidents or disruptions to any users and keeping all facilities open at all times.”
- Rob Soulis, Senior Site Superintendent, Scott Builders
Lessons and Takeaways
The success of the Gary Moe Auto Sportsplex renovation underscores Scott Builders’ expertise in managing complex, phased renovation projects while maintaining operations. Our ability to solve unexpected challenges without compromising quality or schedule highlights our leadership in the construction industry and our commitment to clear communication, expert problem-solving and empowering all stakeholders with the tools for success.
Why Choose Scott Builders
For large-scale renovations, especially those requiring a phased approach, Scott Builders is the partner you can trust. Our solutions-focused, collaborative methods ensure you receive a high-quality product—on time, on budget, and with minimal disruption.